'Third Launch Pad Construction on Hold Until Long-Term Space Plans Finalised'

Advertisement
By Indo-Asian News Service | Updated: 19 March 2015 17:03 IST
Even though the Indian space agency has decided to locate its third launch pad with facilities for a human space mission at its existing rocket port, the construction will happen only after the agency finalises its long-term plans, a top official said.

"Our immediate focus is on completing the second vehicle (rocket) assembly. We can increase the rocket launch frequency after that. The decision to construct the third launch pad will be taken after finalising our long-term action plan," Indian Space Research Organisation (Isro) chairman A.S.Kiran Kumar told IANS.

At present Isro has two rockets - GSLV-MkII and Polar Satellite Launch Vehicle (PSLV) - and two launch pads at Sriharikota in Andhra Pradesh, around 80 km from here.

Advertisement

Queried about the need for a stand-by launch facility for Isro's heaviest rocket currently under development - the Geosynchronous Satellite Launch Vehicle-Mark III (GSLV-MkIII) - Kumar said: "The initial two GSLV-MkIII rockets will be flown using the second launch pad."

The GSLV-MkIII rocket is expected to be flight-ready in December 2016.

Advertisement

In a written reply to a question raised in the Rajya Sabha recently, Minister of State for Science and Technology Jitendra Singh said Isro proposes to set up the third launch pad at Satish Dhawan Space Centre (SDSC), Sriharikota.

He said the third launch pad is intended to support increased launch frequency, launching requirements of future advanced launch vehicles and also serve as a redundant launch pad for the GSLV-MkIII class of rockets.

Advertisement

Detailed studies on possible concepts/options and preliminary configuration have been carried out, he said.

The possible site for the third launch pad has been identified in Sriharikota taking into account the safety distances and maximal utilisation of existing launch pad facilities, he said.

Advertisement

"With plans to develop a much bigger rocket - GSLV-MkIII - and also taking into account the advanced future rockets, a need for a new launch pad was felt within Isro," SDSC director M.Y.S.Prasad told IANS on the phone.

"This apart, with Isro planning a manned mission in the future, the proposed launch pad should also have facilities that allow entry and exit of humans in and out of the rocket," he added.

When bigger and advanced rockets are being planned, the launch pad should also have necessary supporting infrastructure like huge fuel storage facilities for fuelling the rocket engines, Prasad said.

India's current rockets stand around 45-50 metres tall and the future rockets will be around 60-65 metres tall and much more heavier.

According to Prasad, a report on the third launch pad has been prepared by a study team with officials drawn from all the Isro centres.

The report has to be studied and a proposal for the third launch pad has to be submitted to the central government for funds.

Prasad said it would take around five years for the launch pad to come into service from the date of project approval and sanction of funds.

Apart from increasing the launch frequency of Indian satellites, the need for a new launch pad would also be considered, taking into account the opportunities for commercial launches - launching of third party satellites for a fee.

With Isro planning to fly its GSLV-MkIII rocket in 2016, a quicker decision on this project is important, officials said, adding that Isro might hire a consultancy firm to draw out the design as per requirements.

Prasad said the land area for the third launch pad and associated facilities will be around 3-4 sq km.

Meanwhile construction of the Rs. 360-crore second vehicle/rocket assembly building has begun at the SDSC.

"The building is expected to be ready in three years' time and would be connected to the second launch pad. As and when the third launch pad is ready, the new rocket assembly building will be connected to that as well," Prasad said.

 

Get your daily dose of tech news, reviews, and insights, in under 80 characters on Gadgets 360 Turbo. Connect with fellow tech lovers on our Forum. Follow us on X, Facebook, WhatsApp, Threads and Google News for instant updates. Catch all the action on our YouTube channel.

Advertisement

Related Stories

Popular Mobile Brands
  1. Huawei Nova 16, Nova 16z Debut With 50-Megapixel Camera at This Price
  2. New Beats Headphones Surface in Lamine Yamal's Instagram Post
  3. Itel Aqua Launched in India With IP67 Rating, 1,200mAh Battery: See Price
  4. Vivo X Fold 6 Launch Timeline, Key Specifications Leaked Online
  5. HP OmniBook X 14, Ultra 16 Refreshed With Nvidia RTX Spark 'Superchip'
  6. Dell XPS 13 Refreshed With Intel Panther Lake CPUs to Rival MacBook Neo
  1. Asus ROG Edition 20 Lineup Unveiled at Computex 2026 to Commemorate 20 Years of ROG Series Products
  2. Indian Startup Pawzeeble Is Building a Pet-Focused Social Networking Space for Indian Users
  3. Asus ROG Strix Scar 18 (2026) With 240Hz 4K Mini-LED Display Showcased at Computex 2026
  4. Huawei Nova 16 Pro, Nova 16 Ultra Launched With Kirin 9010S SoC, 7,000mAh Battery: Price, Specifications
  5. Huawei Nova 16 Launched With 7,000mAh Battery, 50-Megapixel Camera, Nova 16z Tags Along: Price, Specifications
  6. Computex 2026: AMD Unveils Ryzen 7 7700X3D, Radeon RX 9070 GRE; Extends AM5 Support to 2029
  7. Itel Aqua Launched in India With IP67 Rating, 1,200mAh Battery: Price, Features
  8. Vivo X Fold 6 Launch Timeline Leaked; Tipped to Arrive With MediaTek Dimensity 9500 Chip
  9. HP OmniBook Ultra 16 (2026), OmniBook X 14 (2026) Unveiled With Nvidia's RTX Spark 'Superchip'
  10. Acer Swift Air 14 Launched With Intel Core Series 3 CPU, Lightweight Design at Computex 2026
Download Our Apps
Available in Hindi
© Copyright Red Pixels Ventures Limited 2026. All rights reserved.